Standby
Startup
Building Technologies Division

6.35.10 Description of sequence diagrams

PH_STANDBY (unlimited)
Burner control waits for a request for heat from the controller.
PH_STARTVER
No external or internal release. The respective diagnostic code is delivered.
The change from Standby to Operation is termed startup – triggered by a request for
heat from the controller. If startup includes prepurging, startup begins with the THL1
phase, without prepurging with the THL1A phase.
THL1
Maximum fan ramp-up time to prepurge level. With prepurge phase (t1) >0 or when
there is a request for forced prepurging.
THL1A
Maximum fan ramp-up time to ignition level. With prepurge phase (t1) = 0 and when
there is no request for forced prepurging.
TV (t1)
Prepurge phase.
TBRE
Maximum time required to reach the ignition level after prepurging (reaching the speed
band for ignition load).
TW1
Maximum waiting time until the following functions are completely performed:
- Internal safety tests: These tests start with the beginning of the startup sequence and
already run in the background during the preceding phases
- Combustion optimization: Combustion optimum switched off, or stepper motor in the
start position
- Fan speed adjustment: Feedback when the required fan speed for the ignition load
has been reached for the first time
TVZ
Preignition time (can be parameterized, but minimum is 0.2 seconds).
TSA
Ignition safety time. If no flame is established on completion of this period of time
(including several reignition attempts), the burner control goes to lockout or makes a
restart, depending on the parameter settings.
TSA1
First part of safety time with ignition on. Fuel valve is open.
User Manual LMS14...
6 The settings in detail
545/617
CC1U7471en
28.01.2015

Advertisement

Table of Contents
loading

Table of Contents