Thermo Scientific TRACE 1300 Instruction Manual page 119

Auxiliary ovens
Hide thumbs Also See for TRACE 1300:
Table of Contents

Advertisement

3
Components Installation
Installing the Methanizer Assembly
Note The mixer has the purpose of mixing the hydrogen with the sample.
Figure 136
shows the mixer anchored to the methanizer assembly. This is the best positioning to
facilitate the connection of the fittings.
Analytical Column or TCD
The restrictor is placed on the line of the hydrogen. When installing it, try to minimize
the length of the tubing out the main oven. A metal label indicates the column ID value
that must be set in the Auxiliary Column page.
The hydrogen comes from a line of the Auxiliary Gas module connected to the restrictor
through an union.
WARNING No fitting where hydrogen flows may be installed into the main oven.
The outlet of the methanizer is connected to the FID detector (installed on the TRACE
1310 Auxiliary Oven or on the GC), using the adapter for packed column.
Figure 136
shows a FID installed on the TRACE 1310 Auxiliary Oven.
Thermo Scientific
TRACE 1310 Auxiliary Oven Instruction Manual
93

Hide quick links: