3
Components Installation
Installing the Methanizer Assembly
90
TRACE 1310 Auxiliary Oven Instruction Manual
Figure 133. Methanizer Installation (6)
J3
8. Fix the mixer on the left wall of the methanizer assembly.
a. If not already done, screw the dowel provided into the central hole of the mixer using
a T8 Torxhead wrench. Stop the screwing of the dowel when it starts to grip the
mixer; the dowel must protrude few millimeters from the central hole of the mixer,
do not overtighten. See
Figure 134. Mount the Mixer (1)
b. Screw the mixer into the hole provided on the left wall of the methanizer assembly.
See
Figure
135.
Figure 135. Mount the Mixer (2)
J9
Figure
134.
Mixer
Dowel
RTD Pt100 Probe
Heater Element
Thermo Scientific