Siemens ET 200pro Operating Instructions Manual page 89

Small, extremely rugged and high-performance i/o system with ip65/66/67 degree of protection
Hide thumbs Also See for ET 200pro:
Table of Contents

Advertisement

Connecting the ECOFAST cable connectors
1. Insert the CM IM DP ECOFAST Cu connection module into the interface module.
2. Screw down the CM IM DP ECOFAST Cu connection module to the interface module
3. Press down the interlock mechanism of the ECOFAST cable connectors on the
4. Plug the ECOFAST cable connectors (1L+, 2L+ and PROFIBUS DP) into the sockets of
5. Push up the interlock mechanism of the ECOFAST cable connectors.
ET 200pro distributed I/O system
Operating Instructions, 03/2013, A5E00335544-08
4.6 Connecting the Interface Module to a CM IM DP ECOFAST Cu Connection Module
(torque = 1.5 Nm). Tighten the four screws evenly, working in cross-wise passes. Those
screws are already attached to CM IM DP ECOFAST Cu connection module.
connection module.
the connection module. Observe the mechanical coding of the cable connectors for
feeding and forwarding.
Figure 4-12
Connecting the ECOFAST cable connectors
Connection
89