Pump Control; Setting A Pump Down Group - Siemens HydroRanger 200 Instruction Manual

Table of Contents

Advertisement

Pump Control

Setting a Pump Down Group

Example: Sewage Wet Well
Setting a group of three pumps to pump down a wet well.
Inflow
Set the Common Parameters
Prerequisite: Substitute the details of your application in place of the sample values
provided. If you are bench testing the unit, set your test values to be the same as the
sample values.
Parameter
P001
P002
P003
P004
P005
P006
P007
1.
Example assumes a single measurement unit. If your HydroRanger 200
has dual point software installed then some parameters are indexed by
two.
Page 56
P006
P007
1
Value Description
Index
G
1
G
1
G
2
G
102
G
1
G
1.8
G
1.4
HydroRanger 200 – INSTRUCTION MANUAL
Operation = level
Material = liquid
Maximum Process Speed = medium
Transducer = XPS-10
Units = meters
Empty = 1.8 m
Span = 1.4 m
HydroRanger 200
Outflow
7ML19985FC03