Completing the installation

To complete the installation, you must reinstall the top cover,
reinstall the bezel, reconnect all cables that you discon-
nected, and, for certain options, run the Configuration/Setup
Utility program. Follow the instructions in this section.
Attention:
To complete the installation, you must reinstall the top cover,
reinstall the media-bay bezel, reconnect all the cables that
you disconnected earlier and, for certain options, run the
Configuration/Setup Utility program. Follow the instructions
in this section.
Attention:
Note: If you have just plugged the power cords of the server
into an electrical outlet, you will have to wait approxi-
mately 20 seconds before pressing the power-control
button.

Installing the server top cover and bezel

The following illustration shows how install the server top
cover.
Note: The illustrations in this document might differ slightly
from your hardware.
1
Top cover
2
Right release latch
3
Bezel
4
Left release latch
5
Cover release latch
For correct cooling and airflow, install the top
cover before turning on the server. Operating
the server for extended periods of time (over
30 minutes) with the top cover removed might
damage server components.
For correct cooling and airflow, install the top
cover before turning on the server. Operating
the server for extended periods of time (over
30 minutes) with the top cover removed might
damage server components.