4. Remove the battery:
5. Insert the new battery:
6. Install fans 3 and 4 in the server (see "Replacing fan 3 or 4" on page 33 for
7. Close the server cover, and connect the cables.
8. Turn on the server.
9. Start the Configuration/Setup Utility program and set configuration parameters.

Completing the installation

To complete your installation, close the server cover, install your server in a rack,
reconnect all cables that you disconnected earlier, and for certain options, run the
Configuration/Setup Utility program. Follow the instructions in this section.
Attention:
after turning on the server. Operating the server for extended periods of time (over
15 minutes) with the server cover open might damage server components.
36
xSeries 450: Option Installation Guide
a. Use one finger to press the top of the battery clip away from the battery.
b. Lift and remove the battery from the socket.
a. Use one finger to press the top of the battery clip away from the battery.
b. Press the battery into the socket until it clicks into place. Make sure that the
battery clip holds the battery securely.
details).
v Set the system date and time.
v Set the power-on password.
v Reconfigure your server.
For proper cooling and airflow, close the server cover before or shortly