Site Preparation Checklist for the SRX5400 Services
Gateway
The checklist in
Table 30 on page 147
services gateway installation.
Table 30: Site Preparation Checklist
Item or Task
Verify that environmental factors such as
temperature and humidity do not exceed
services gateway tolerances.
Select the type of rack or cabinet.
Plan rack or cabinet location, including
required space clearances.
Plan electrical power provisions.
If a rack is used, secure rack to floor and
building structure.
Acquire cables and connectors.
Locate sites for connection of system
grounding.
Measure distance between external
power sources and services gateway
installation site.
summarizes the tasks you need to perform when preparing a site for
For More Information ...
"SRX5400 Services Gateway Environmental
Specifications" on page 148
"SRX5400 Services Gateway Cabinet Size and
Clearance Requirements" on page
"SRX5400 Services Gateway Rack Size and
Strength Requirements" on page 152
"Clearance Requirements for SRX5400 Services
Gateway Airflow and Hardware Maintenance" on
page 151
"Calculating Power Requirements for the SRX5400
Services Gateway" on page 154
"Connection to Building Structure for the SRX5400
Services Gateway Rack" on page 153
DC Power Electrical Safety Guidelines and Warnings