Checklist 1: Install New G700 with an S8300 (Primary or LSP) (continued)
Major Tasks
If using IA770, install
messaging software
page 149
Configure the G700 Media
Gateway
on page 150
Install New Firmware on the
G700
on page 160
Administer Communication
Manager
on page 169
Considerations for IP Phones
Supported by a Local Survivable
Processor
on page 186
Set Up SNMP Alarming on the
G700
on page 188
Complete the Installation of the
S8300 (if the Primary
Controller)
on page 191
Subtasks
- Log in to the S8300 platform
on
- Stop the system
- Auto-install the messaging software
- Restart the system
- Enable messaging on the S8300 Web
interface
- Assign IP addresses to the G700 processors
- Set up IP routing for the stack
- Set up default IP route for the G700
- Check IP connections
- Set up controller list for the G700
- Configure X330 Expansion Module, if
necessary
- Verify contents of the tftp directory
- Determine which firmware to install
- Install firmware on the P330 stack processor
-Set Rapid Spanning Tree
- Install firmware on the G700 media gateway
processor
- Install firmware on the media modules
- Install firmware on other G700s in the stack or
network, if any
- Reboot the system
- Assign node names, if necessary
- Administer network regions
- Assign LSPs to network regions
- Administer IP interfaces
- Administer the LSP form
- Add media gateway
- Verify changes
- Enable announcements, if necessary
- Save translations
- Register the system
- Back up the system
- Check planning documentation
- Connect and administer test endpoints
- Complete electrical installation
- Enable adjunct systems
About the Installation Roadmap and Task Lists
Issue 7 January 2005