3.7 Installation Verification

After installing a unit, check the components listed in
Table 3-12 Check items after the indoor unit installation
Check
Item
Cabinet
Issue 06 (2020-01-13)
During the installation, grasp the panel frame instead of the blade to move the panel to
avoid blade deformation.
The cap should be well sealed to the smart cooling product to ensure good sealing
performance in-between.
Expected Result
The cabinet is installed properly, without any tilt.
The cabinet is secured to the support by using bolts.
Copyright © Huawei Technologies Co., Ltd.
3 Installation Guide
Table
3-12.
Actual Result
□Passed □Failed
□Passed □Failed