Installation Precautions - Huawei FusionCol8000-E260 Quick Manual

Modular indirect evaporative cooling system
Hide thumbs Also See for FusionCol8000-E260:
Table of Contents

Advertisement

FusionCol8000-E260 Modular Indirect Evaporative
Cooling System
Quick Guide (FDC Scenario)
Checking the Auxiliary Facilities
Checking the Drainage Capacity
There should be drainage ditches with sufficient drainage capacity.
The layout and installation of pipes should facilitate the maintenance of the unit.
Checking Electrical Access for Auxiliaries
Install the unit in strict accordance with the HVAC system construction regulations.
To ensure proper operation of the unit, protect it against dust, dirt, corrosive gas,
and high humidity.
Connection Engineering Precautions
Issue 01 (2022-06-30)
1
The horizontal and height errors between concrete platforms must be less
than 5 mm.
Concrete pads or passages with the bearing capacity meeting local civil work
standards can be built on the field outside the concrete platforms for access
and maintenance.
NO TICE
Air duct installation: It is recommended that flexible connections be used
between the unit and air duct. Prepare air ducts based on site requirements.
Pipe thermal insulation: Take thermal insulation measures for all inlet pipes
and drainpipes of the unit. Reserve sufficient space for maintenance and
operations when installing thermal insulation foam for valves and connectors.
At low temperatures, take thermal insulation measures to prevent water pipes
from freezing.