Activity
Have the digital and analog signals been routed with separate cables?
Has the distance from power cables been observed?
Has the cabinet been properly grounded at the points provided?
Has the connection voltage for the fans in the chassis components been adapted
accordingly to the supply voltages?
For operation on non-grounded supply systems: Has the connection bracket for the
interference suppression at the Infeed Module or the Power Module been removed?
Is the period from the date of manufacture to the initial commissioning or the downtime
of the power components less than two years
Is the drive operated from a higher-level controller/control room?
Combined fuses are recommended for conductor and semi-conductor protection (VDE 636,
1)
Part 10 and Part 40 / EN 60269-4). For information about the relevant fuses, see the catalog.
If the downtime period is longer than two years, the DC-link capacitors must be formed (see the
2)
"Maintenance and Servicing" chapter in the Equipment Manual). The rating plate can be used to
ascertain the date of manufacture.
Commissioning with Startdrive
Commissioning Manual, 11/2017, 6SL3097-4AA10-0BP1
4.3 Check lists to commission SINAMICS S
?
2)
Commissioning
OK