Connect The Power Cords - Oracle Exalogic Elastic Cloud Owner's Manual

Table of Contents

Advertisement

Check the rack for loose or missing screws.
2.
Check your Exalogic machine for the ordered configuration. Refer to the
3.
Customer Information Sheet (CIS) on the side of the packaging.
Check that all cable connections are secure and firmly in place as follows:
4.
a.
b.
Check the site location tile arrangement for cable access and airflow.
5.
Check the data center airflow that leads in to the front of the Exalogic machine.
6.

3.3.2 Connect the Power Cords

The following procedure describes how to connect power cords to the Exalogic
machine:
Open the rear cabinet door.
1.
Ensure that the correct power connectors have been supplied.
2.
Unfasten the power cord cable ties. The ties are for shipping only and are no longer
3.
needed.
Route the power cords to the facility receptacles either above the rack or below the
4.
flooring, as shown in
Secure the power cords in bundles, as shown in
5.
Plug the PDU power cord connectors into the facility receptacles.
6.
Check the power cables. Ensure that the correct connectors have been
supplied for the data center facility power source.
Check the network data cables.
See Also:
Ventilation and Cooling
Figure 3-9
Requirementsfor more information
and
Figure
3-10.
Figure
Install Planning and Procedure 3-13
Power on the System the First Time
3-9.