9.4 Sway control commissioning
The positions for the prelimit switch velocity (P24, P27) must be set so they lie before the limit
switch position or exactly at the limit switch position. This ensures that the trolley drive was
decelerated to the prelimit switch velocity when the limit switch is reached.
Note
During deceleration to the prelimit switch velocity, the sway control system is only active with
restrictions.
If the delay to prelimit switch velocity is to be subject to sway control, the setpoint must be
reduced in the crane control system.
Note
If P24 > P27, the trolley always travels at prelimit switch velocity.
If P64 > P68, the hoist always travels at prelimit switch velocity.
330
SC integrated STS, GSU
Operating Instructions, 07/2019, A5E48271265B AA

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics

Table of Contents