Artisan Technology Group - Quality Instrumentation ... Guaranteed | (888) 88-SOURCE | www.artisantg.com
This test verifies that the external reference input operation is functioning
correctly.
The following equipment is required.
Equipment Required
Connections. Refer to Figure B-6 for connections.
Use the SMA cables and the SMA female-to-BNC male adapters to make the
following connections:
H Connect CH1 output from the DG2040 Data Generator front panel to the
oscilloscope CH1 input.
H Connect CH1 output to the DG2040 Data Generator front panel to the
oscilloscope CH2 input.
Use the BNC cables to make the following connections:
H Connect the function generator CH1 output to the DG2040 Data Generator
rear panel event input.
H Connect the function generator CH2 output to the DG2040 Data Generator
rear panel reference input.
H Connect the event output from the DG2040 Data Generator rear panel to the
oscilloscope CH3 input.
H Connect the sync output from the DG2040 Data Generator rear panel to the
oscilloscope CH4 input.
Oscilloscope
Function generator
Four BNC cables
Two SMA cables
Two SMA female to BNC male adapters