FRU
Fan canister (60-drive shelves only)
Drive drawer (60-drive shelves only)
Related information
NetApp E-Series Systems Documentation Site
Replace storage controller
Replace hardware components in optional 60-drive expansion shelf
You might need to replace an input/output module, a power supply, or a fan in the
expansion shelf.
What you'll need
• You have the E-Series hardware replacement procedure.
• You have physically located the storage appliance where you are replacing expansion shelf hardware
components in the data center.
Locate controller in data center
About this task
To replace an input/output module (IOM) in a 60-drive expansion shelf, see the instructions in these
instructions for replacing a storage controller.
To replace a power supply or a fan in a 60-drive expansion shelf, access the E-Series procedures for
maintaining 60-drive hardware.
FRU
Input/output module (IOM)
Power canister
Fan canister
Shut down SG6000-CN controller
Shut down the SG6000-CN controller to perform hardware maintenance.
What you'll need
• You have physically located the SG6000-CN controller requiring maintenance in the data center.
Locate controller in data center
• The appliance has been
placed into maintenance
See instructions
E-Series: Replace fan canister (60-drive)
E-Series: Replace drive drawer (60-drive)
See E-Series instructions for
Replacing an IOM
Replace power canister (60-drive)
Replace fan canister (60-drive)
mode.
139