Preparation can be performed after installation or on the bench.
Note: If using the existing detector, refer to "11. HOW TO CHANGE THE SETTING".
(1) Wiring check (Refer to "4.3", "4.4")
(2) Confirmation of the power supply specifications (Please check the main power supply and the
power supply voltage specification of the detector.)
(3) Power ON.
Open the front flap. Turn "ON (–)" the power switch. (Refer to "2.2.2")
OXYGEN ANALYZER
VER . YY/MM
WARM-UP
HEATER 234 °C
(4) Warm-up (After 10 minutes from power ON, accurate measurement data may be obtained.)
(5) Parameter setting
Move to each Menu with reference to the paragraph "5.2 Key operation flow diagram (outline)",
and set a necessary parameter. Refer to the paragraph "5.3 Initial parameter value table".
If you need to change a parameter, refer to the "Chapter 10".
(6) Calibration
At the first operation, perform manual calibration after warm-up using a calibration gas.
Refer to "chapter 7" for calibration procedures.
(7) Auto calibration (option)
Automatic calibration may be performed at specified time intervals.
Refer to "7.3" for automatic calibration settings.
(8) Blowdown (option)
A flow guide tube blowdown feature prevents the flow guide tube from clogging due to dust in
the gas stream.
Refer to "chapter 8" for operation procedures.

5. OPERATION

5.1 Preparation for operation

The message shown left appears on the LCD screen.
After about 6 seconds, the display is automatically switched to the
warming-up screen.
Operation