25. Install the fixed sheave shields, and deflector sheaves
using the retaining bolts and washers. Coat the bolts
with JLG Threadlocker P/N 0100011 before installation.
Torque the bolts to 28 ft.lbs. (38 Nm).
26. Coat the bolts with JLG Threadlocker P/N 0100011 and
install the section 5 retract ropes to section 3 using the
nuts, keeper plates, bolts, and washers.
3121619
SECTION 4 - BOOM & PLATFORM
27. Coat the bolts with JLG Threadlocker P/N 0100011 and
install the section 5 extend ropes to section 3 using nuts,
keeper plates, bolts, and washers.
28. Coat the bolts with JLG Threadlocker P/N 0100011 and
install the front bottom wear pads to section 3 using
washers, bolts, and shims. Torque the bolts to 43 ft.lbs.
(58 Nm)