3.
Remove the PEEK tubing from the reset button aperture.
4.
Wait until the reboot sequence ends before starting the MassLynx
software.
An audible alert sounds when the reboot sequence is complete.
Tip:

Leaving the mass spectrometer ready for operation

Leave the mass spectrometer in Operate mode except in the following cases:
When performing routine maintenance
When changing the source
When leaving the mass spectrometer unused for a long period
In these instances, put the mass spectrometer in Standby mode. See the
online Help for details.

Emergency shutdown of the mass spectrometer

To shut down the instrument in an emergency:
Warning:
main power supply. To isolate the instrument, follow the procedure
outlined below.
Caution:
1.
Operate the power button on the front of the instrument.
2.
Disconnect the power cable from the instrument's rear panel.
The instrument's power switch does not isolate it from the
Data can be lost during an emergency shutdown.