Commissioning Monitoring Components; Commissioning Access Control Components - Huawei FusionModule1000B V100R003C00 Commissioning Manual

Water-cooled it solution
Table of Contents

Advertisement

FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
Step 2 Start the civil air conditioners by referring to the delivered documents.
Step 3 Commission the civil air conditioner by following the instructions in the delivered documents.
----End

9.3 Commissioning Monitoring Components

9.3.1 Commissioning Access Control Components

Prerequisites
Preparations
Tools: step ladder, Phillips screwdriver
Document: monitoring device layout diagram
Skill requirement: weak-current engineer familiar with the management system
Procedure
Step 1 Open the physical lock.
Step 2 Open the electronic door lock by swiping an access card.
Step 3 Rotate the door handle clockwise and pull open the container door.
Step 4 Enter the container and close the container door.
Step 5 Push the emergency exit rod, and check whether the emergency exit door opens properly.
Step 6 Verify that the management system generates a door open alarm.
Step 7 Press the exit button and push open the container door.
Issue 02 (2017-01-10)
Before the power-on commissioning, ensure that the air supply and return vents of the air
conditioners are not blocked, and condensate drainpipes are intact and not blocked.
If any alarm is raised, rectify the fault before continuing the commissioning.
You have powered on the access control system.
You have configured the IC cards.
For the diagrams, see the initial configuration parameter manual for the solution in use.
If you do not open the container door in 6s after swiping the card, the electronic lock locks the container
door again.
Normal response: The container door can be opened, and the management system logs the door opening
event.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Commissioning Core Components
94

Advertisement

Table of Contents
loading

Table of Contents