FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
Purpose
This document describes how to power on and commission the FusionModule1000B
prefabricated modular data center solution (FusionModule1000B for short) in terms of
power-on commissioning preparations, checking items and precautions, power-on check,
power-on commissioning, joint commissioning, and power-off. This document also describes
the power-on commissioning, joint commissioning, and power-off methods for core
components of the solution. It provides you a quick grasp of the commissioning method.
Intended Audience
This document is intended for:
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol
Issue 02 (2017-01-10)
Commissioning engineers
Technical support engineers
System engineers
Maintenance engineers
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
About This Document
Description
Indicates an imminently hazardous situation which, if
not avoided, will result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, could result in death or serious injury.
Indicates a potentially hazardous situation which, if not
avoided, may result in minor or moderate injury.
About This Document
ii