Initial Dip Configuration For The Main Control Board - Huawei FusionModule1000B V100R003C00 Commissioning Manual

Water-cooled it solution
Table of Contents

Advertisement

FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
Figure 9-3 DIP switch on a remote T/H sensor
Procedure
Step 1 Verify the DIP switch settings for each 30 kW chilled water precision air conditioner by
referring to the initial DIP switch configuration table for the remote T/H sensor of the 30 kW
chilled water precision air conditioner.
----End

9.2.2.2 Initial DIP Configuration for the Main Control Board

Prerequisites
You have powered on the 30 kW chilled water precision air conditioners.
Preparations
Tools: none
Document: initial DIP switch configuration table for the main control board of the 30 kW
chilled water precision air conditioner
Skill requirement: cooling engineer
Context
You need to set the DIP switch on the main control board of a 30 kW chilled water precision
air conditioner before starting the air conditioner.
Issue 02 (2017-01-10)
Remote T/H sensors are configured before delivery. You only need to verify the DIP switch settings by
referring to the initial DIP switch configuration table for the remote T/H sensor of the 30 kW chilled
water precision air conditioner.
If any DIP switch setting is inconsistent with the initial setting, change it to the initial setting.
For the tables, see the initial configuration parameter manual for the solution in use.