FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
Documents required: documents delivered with the VESDA, fire extinguishing device layout
diagram, power supply and distribution system diagram
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker of the VESDA for the protected area by referring to
the power supply and distribution system diagram.
Step 2 (Optional) Perform power-on commissioning by following instructions in documents
delivered with the VESDA.
Step 3 Release smoke in the protected area using the smoke pistol. Verify that the VESDA alarm
indicator lights up, and that an alarm is generated in the management system.
----End
Issue 02 (2017-01-10)
For the diagrams, see the initial configuration parameter manual for the solution in use.
The VESDA is commissioned before delivery. A VESDA that is newly installed or used as a replacement
must be commissioned as instructed by the delivered documents.
After the operation is complete, press the reset button to reset the VESDA.