FusionModule5000 Smart Modular Data Center
Commissioning Guide
Check Method
when the aisle door is closed.
Step 5 Check functions of the magnetic lock.
Table 6-20 Function commissioning
Check Method
When the aisle door is
normally closed, check
whether there is a door open
alarm on the ECC800.
----End

6.6.4 NetEco Management

6.6.4.1 Connecting the Communications Cable

Procedure
Step 1 Connect the communications cable to the WAN_1 port on the ECC800.
Figure 6-22 Connecting the communications cable
----End

6.6.4.2 Setting NetEco Parameters

When the smart module can be connected to the NetEco, perform the following steps to
configure parameters.
Issue 06 (2020-03-20)
Normal Connection
Status
Normal Connection
Status
There is no door open
alarm on the ECC800.
Copyright © Huawei Technologies Co., Ltd.
6 Commissioning the Management System
Follow-up Procedure
Troubleshooting
If a door open alarm is reported
when the door is closed,
relocate the magnetic lock and
magnet to minimize the
deviation until the door open
alarm is cleared.