FusionModule5000 Smart Modular Data Center
Commissioning Guide
Procedure
Step 1 Install cables between the fire controller and ECC800.
Figure 6-9 Installing cables between the fire controller and ECC800
Step 2 Log in to the ECC800 WebUI as an administrator.
Step 3 Set the Linkage Group status.
Figure 6-10 Setting the Linkage Group status
Step 4 Modify the AI/DI_6 signal name and click Submit.
Issue 06 (2020-03-20)
Select Link fire control with smart cooling product off under Linkage Group. If its value is on, the
corresponding logic configurations under Linkage Logic List are available. If its value is off, the
corresponding logic configurations under Linkage Logic List are unavailable.