Figure 6-44 Cooling capacity parameters
Step 4 Choose Monitoring > System. Click Cooling Capacity Information on the Running Info
tab page to query the cooling capacity parameters of the smart module.
Step 5 If the cooling load factor of the smart module exceeds 95%, a cooling margin insufficient
alarm will be raised, which will be cleared when the cooling load factor is smaller than 93%.