5.9 (Optional) Power-off

Context
In shutdown mode, the Shutdown button is green (unavailable) and the Start button is gray
(available).
Procedure
Step 1 Tap Shutdown on the home screen. A warning is displayed, indicating whether to shut down
the smart cooling product, as shown in
Issue 06 (2020-03-20)
Figure 5-18 Commissioning successfully
Figure 5-19
is displayed if component commissioning fails, which ends startup wizard
commissioning.
Figure 5-19 Commissioning unsuccessfully
If commissioning fails, tap Commissioning failed. in
Copyright © Huawei Technologies Co., Ltd.
5 Commissioning the Cooling System
Figure 5-19
to view the details.
Figure
5-20.
49