FusionModule5000 Smart Modular Data Center
Commissioning Guide
5
5.1 Power-On
Procedure
Step 1 Turn on the smart cooling product switch in the power distribution cabinet and the AC1 and
AC2 switches on the smart cooling product.
Step 2 After the system is powered on for the first time, the Quick Settings screen is displayed. Log
in as the admin user, as shown in
Figure 5-1 Initial power-on
Table 5-1 Preset password
User
admin (administrator
user)
operator (common
user)
Issue 06 (2020-03-20)
Commissioning the Cooling System
Preset Password
000001
000001
Copyright © Huawei Technologies Co., Ltd.
Figure
5-1.
Permission Description
People can operate all menus.
People can only view parameter settings
and set a part of parameters in the
menus.
5 Commissioning the Cooling System
25