Figure 5-5 Teamwork settings
Step 2 Set teamwork control parameters.
All teamwork control parameters can be set on the master smart cooling product. Only
Teamwork group No., Air conditioner address, Enable teamwork CAN resistor,
Teamwork function and Networking mode can be set on slave smart cooling products.
Other parameters of the slave units will be modified by the master unit synchronously.
5-5
Table 5-5 Teamwork settings
Parameter
Teamwork
group No.
Air conditioner
address
Enable
Teamwork
CAN resistor
Teamwork
function
Issue 06 (2020-03-20)
describes how to set the parameters.
Description
Set the assigned
teamwork control
number.
Set the assigned smart
cooling product address.
Indicates the build-out
resistor status of each
smart cooling product in
a teamwork group. Set
the parameter if CAN
network is used.
Disable or enable the
teamwork function. If the
teamwork function is
Copyright © Huawei Technologies Co., Ltd.
5 Commissioning the Cooling System
Configuration
Principle
The number of the
teamwork controlled
group, which is the same
for all the devices in the
group.
Smart cooling product
addresses should be
different from each other.
Set this parameter to
No for non-teamwork
scenarios.
For teamwork
scenarios, set this
parameter to Yes for
the first and last smart
cooling products in a
teamwork group, and
set it to No for other
smart cooling products.
Set this parameter based
on the onsite device heat