VIFB16 - 03/05
4-6
4. Commissioning
Switching on the operating voltage
When the control system is switched on, the
controller compares the nominal and the actual
configuration. For the configuration run it is
important that:
•
the specifications on configuration are as
complete as possible and are correct;
•
the power supply to the controller and to the
connected slaves is made either simultane-
ously or in the correct sequence.
PLEASE NOTE
Observe the switching on instructions in the
manual for the PLC/PC.
0506b