2. Commissioning CPV−DI02 (PROFIBUS−DP)
2.1

Preparing the CPV Direct for commissioning

2.1.1 Switching on the power supply

Common supply
Separate supply
Festo P.BE−CPV−DI02−EN en 0704NH
Note
Please observe also the switching−on instructions in the
manual for your PLC.
When the controller is switched on, it will automatically carry
out a comparison between the NOMINAL and the ACTUAL
configurations. It is important for this configuration run that:
the specifications for the field bus configuration are com
plete and correct.
the power supplies for the programmable logic controller
and for the field bus slaves are switched on either simul
taneously or in the sequence indicated below.
Please note the following when switching on the power
supply:
Common power supply for the control system and all field
bus slaves via a central power unit or a central switch.
If there is a separate supply for the control system and for the
field bus slaves, the power should be switched on in the
following sequence:
1. the operating voltage supply for all field bus slaves
2. the operating voltage supply for the controller.
2−3

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cpv-di02Profibud-dpCpv-cs02Abb cs31Profibus-dpCpv-di02 profibus-dp series ... Show all

Table of Contents