2. Commissioning CPV−DI02 (PROFIBUS−DP)
Icons
Festo P.BE−CPV−DI02−EN en 0704NH
Note
As from STEP 7 V4.02, GSDs are stored within the STEP 7
project (station GSD). This can cause the updating/reading
of new GSD files to appear as if incorrect. Please inform
yourself about handling the station GSD files in the STEP 7
help.
2. Process the dialogue window Properties PROFIBUS"
Baud rate
Profile
3. Copy the icon files (see section 2.2) for the CPV Direct
into directory ...\STEP7\S7DATA\NSBMP on your PC or
programmer.
The icon files can either be:
copied manually into the above named directory or
loaded via the menu [Options] [Install new GSD] file
type Bitmap files" in HW Config.
4. Insert a DP master system:
Right−hand mouse click on DP" under CPU" in the rack.
Click on [Add master system] in the context menu.
The line of the DP master system will be displayed.
2−11