INSTALLATION
4.3

Shipment Inspection

After components are unloaded, inspect them for shipping damage. If needed,
carefully remove protective plastic wrapping from components.
NOTE:
If damage is found, notify shipper immediately.
4.4

Steps for Installation

The procedures below are the sequence of steps to complete installation.
Install the positioner (see Section 4.6).
Install the robot common base (see Section 4.7).
Install the programming platforms (see Section 4.8).
Install the auxiliary equipment common (AEC) base (see Section 4.9).
Connect the cables (see Section 4.10).
Install fencing (see Section 4.11).
Install the cell door (see Section 4.12).
Install arc curtains on fencing (see Section 4.13).
Install light curtains (see Section 4.14).
Install the operator station (see Section 4.15).
Connect the power (see Section 4.16).
Conduct a system check before system power up (see Section 4.17).
Power up the system (see Section 4.18).
Light Curtain Alignment/Fence Anchoring (see Section 4.19).
Conduct a system check after system power up (see Section 4.20).
Installing tooling and fixtures (see Section 4.21).
4.5

Shipping/Leveling Bolts

Components of the ArcWorld IV-6200 XHD DR2C cell are secured to wood
boards or shipping skids with multiple shipping/leveling bolts (see Figure 4-3).
Once the shipping bolts are removed, the leveling bolts are maintained to level the
component before anchoring. Figure 4-4 shows factory-supplied anchors (with
nuts/washers) used to anchor components to concrete floor.
ArcWorld IV-6200 XHD DR2C System Manual

Figure 4-3 Shipping/Leveling Bolts

4-4
SHIPPING BOLT
LEVELING BOLT
MOTOMAN