The system requires preventive maintenance for safe and
reliable operation. Refer to the schedule below for the minimum
periodic maintenance requirements.
As Needed – Perform these tasks as conditions require:
• Cleaning (Section 6.1.1).
• Quick flow cell cleaning when recommended by a system
alert message (Section 6.4).
• Wipe cone on PurIon system with wipe soaked with
methanol or water to remove visible residue near cone
inlet. (PurIon systems only).
Every Run – Perform these tasks at the end of each run:
• Allow the separation run to finish with a high
percentage of solvent B to flush residual compounds
from the column, internal tubing, and flow cell. Refer to
section 6.4.
• Allow Cone wash to run to completion (PurIon systems
only) to wash residual compounds from the fluid
interface, probe, and to clean the cone area.
• Allow Valve Wash sequence to run to completion to wash
residual compounds from the injection valve and ELSD
(if installed) flow path.
Monthly – Perform these tasks at least monthly, more fre-
quently if conditions warrant:
• Tubing Inspection (Section 6.2.1).
• Collection rack and tray cleaning (Section 6.1.2).
• Monthly flow cell cleaning (Section 6.4.3).
Annually – Perform these tasks at least annually, more fre-
quently if conditions warrant:
• Change roughing pump oil (PurIon systems only).
ACCQPrep HP125
Section 6 Maintenance
Vacuum or pressurized
air applied to the outlet
end of the drain tube
must exist at the
collection tray drain hole.
6-3

Advertisement

Table of Contents
loading

Table of Contents