Commissioning the inverter with know-how protection
Procedure - overview
Proceed as follows to commission an inverter with know-how protection:
1. Commission the inverter.
2. Create the exception list (Page 339).
3. Activate the know-how protection (Page 338).
4. Save the settings in the inverter by copying RAM to ROM with
5. Save the project with
You have commissioned the inverter with know-how protection.
Inverter with CU230P-2 Control Units
Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
(machine type, password, etc.) that may be required for the support of the end customer.
Backing up data and series commissioning
on the PG/PC. Also back up any other project-related data
9.5 Write and know-how protection
or via p0971 = 1.