Backing up data and series commissioning

External data backup
After commissioning, your settings are saved in the inverter so that they are protected
against power failure.
We recommend that you additionally back up the settings on a storage medium outside the
inverter. Without backup, your settings could be lost if the inverter developed a defect (see
also Replace Control Unit (Page 345)).
The following storage media are available for your settings:
● Memory card
● PG/PC
● Operator panel
Note
Data backup using operator panels with USB connection with the PG/PC is not possible
If the inverter is connected to a PG/PC via a USB cable, you can save any data on the
memory card using an operator panel.
• Before you save data to the memory card using an operator panel, disconnect the USB
Carrying out series commissioning
Series commissioning is the commissioning of several identical drives.
Precondition
The Control Unit to which the settings are transferred has the same order number and the
same or a higher firmware version as the source Control Unit.
Overview
You must proceed as follows to carry out series commissioning:
1. Commission the first inverter.
2. Back up the settings of the first inverter to an external storage medium.
3. Transfer the settings of the first inverter to another inverter via the storage medium.
See also the following sections:
● Backing up and transferring settings using a memory card (Page 324)
● Saving settings on a PC (Page 331)
● Saving settings on an operator panel (Page 332)
Inverter with CU230P-2 Control Units
Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG