9.4.3

Operation switch wiring

The operation switch is connected to the PLC through an external cable and the Connector Conversion Box.
■1. Connection example
■2. Pin layout
Model name
SW-COM
Connector Conversion
Terminal block 2
Box
9.4.4

Operation switch input

The operation switch (SW1 to SW6) can directly connect to the PLC input and be used in the sequence program as general
input devices.
• The operation switch is loaded into the PLC as the momentary switch of the a contact.
When wired to PLC X0
X0
• In the case of handling the input as the b contact or the alternate switch, create the input in the sequence program.
Handy GOT
SW-COM
SW1
SW2
SW3
SW4
SW5
SW6
SW1
SW2
Terminal block 2
Terminal block 2
1
2
Operation switch action
Y0
X0
Connector
conversion box
Terminal
block 2
1
2
3
4
5
6
7
Terminal No.
SW3
SW4
Terminal block 2
Terminal block 2
3
4
ON
OFF
ON
OFF
PLC
COM
X0
X1
X2
X3
X4
X5
SW5
SW6
Terminal block 2
Terminal block 2
5
6
9.4 Switch Wiring
7
9
9 - 13