7. Maintain the cable routing while moving the head the rest of the way onto
the boom.
In doing so, the cable should form a loop and exit at the power connector
end (rear) of the head. Refer to Figure 1-9.
WARNING:
Install the end stop at the tip of the boom now! Failure
to do so could cause the head to be accidentally pushed from the
boom during the steps that follow.
8. Verify that the cable is properly routed. Refer to Figure 1-9.
9. Connect the power cables from the boom and from the head (see Figure 1-
9).
10. Move the head to its limit against the end stop at the boom tip. Pull out any
slack left in the cable and secure to the wire tie securing block at the end
of the head.
11. Roll the head back and forth several times while observing the cable rout-
ing to ensure it is properly placed.
12. Switch on the OLP power.
13. Switch on the power at the crane control panel and check the operation of
the unit.
14. Operate the crane in the up direction until the steel ball recedes into the
cover. Check that the upper limit switches activate before the ball fully
recedes into the cover. Adjust the switches as required.
15. Re-install the OLP top side panel and the crane head end cover.
16. Refer to the Avantra 36/44 User Guide for operation instructions.