Installing the Routing Engine RE-S-X6-64G

Copyright © 2016, Juniper Networks, Inc.
Grasp the Routing Engine by the ejector handles, and slide it about halfway out of the
6.
chassis.
Place one hand underneath the Routing Engine to support it, and slide it completely
7.
out of the chassis. Place the Routing Engine on the antistatic mat.
NOTE:
To maintain proper airflow through the chassis, do not leave an SCB
installed in the chassis without a Routing Engine for extended periods of time.
If a Routing Engine is removed, a replacement Routing Engine should be
installed as soon as possible.
To install the new Routing Engine (RE-S-X6-64G):
Attach an ESD grounding strap to your bare wrist and connect the strap to one of the
1.
ESD points on the chassis.
Ensure that the ejector handles are not in the locked position. If necessary, flip the
2.
ejector handles outward.
Place one hand underneath the Routing Engine to support it and carefully align the
3.
sides of the Routing Engine with the guides inside the opening on the SCBE2.
NOTE:
The Routing Engine RE-S-X6-64G is supported only on the SCBE2.
RE-S-X6-64G is not compatible with the SCB or the SCBE.
Slide the Routing Engine into the SCBE2 until you feel resistance, and then press the
4.
Routing Engine's faceplate until it engages the connectors.
Press both of the ejector handles inward to seat the Routing Engine. Tighten the
5.
captive screws on the top and bottom of the Routing Engine.
Connect the management device cables to the Routing Engine. After the Routing
6.
Engine is installed, the
Verify that the SCBE2 and RE-S-X6-64G Routing Engine are online by issuing the
7.
show chassis hardware
After you install the RE-S-X6-64G Routing Engine into the SCBE2, the Routing Engine
8.
gets automatically powered on and comes up in amnesiac mode as it is loaded with
factory defaults. After the Routing Engine comes up in amnesiac mode, load the base
configuration and commit.
The Routing Engine might require several minutes to boot. After the Routing Engine boots,
verify that it is installed correctly by checking the
interface. If the router is operational and the Routing Engine is functioning properly, the
green
LED on the Routing Engine lights steadily. If the red
ONLINE
instead, remove the Routing Engine and reinstall it. If the red
Chapter 24: Replacing Host Subsystem Components
ONLINE
LED starts blinking green slowly.
command.
FAIL
,
, and
LEDs on the craft
RE0
RE1
LED lights steadily
FAIL
FAIL
LED on the Routing
277