3. Adjust the "Backboard Extension" 34 vertically so that
it just touches the backboard at the "Clearance Point"
37 .
(See Fig. # 3-32)
Fig. # 3-32 Backboard Extension Installation
4. Use a Powered Drill to install a "Tek Screw" 38 in each
of the eight holes, being careful not to over tighten the
screws. You may need to rotate the auger to access
some of the screws. Repeat this process at each hanger
bearing on the Power Sweep backboard.
Fig. # 3-33 Backboard Extension Installation
34
37
(See Fig. # 3-33)
38