Mechanical Installation
To install a pedestal-mounted D-frame unit, perform the
following steps as shown in Figure 6.100:
1.
Attach the pedestal to the backchannel using two
M10 nuts
2.
Fasten two M5 screws through the back pedestal
flange into the pedestal drive mounting bracket
3.
Fasten four M5 screws through the front pedestal
flange into the front connector plate mounting
holes
6
6
1
3
Figure 6.100 Pedestal Hardware Installation