Toyota Orderpicker Model 7BPUE 15 Service Manual
Mast Section
7- 1 12.
Figure
7- 1 13.
Figure
12. Remove operator platform.
Installation
1. With suitable hoist, lower bottom bearings
on carriage into channel on inner mast.
2. Make sure there are sufficient shims to
prevent side play. See "Mast Bearings" on
page 7-85.
3. Make sure 2 switches (S6 and S7) a t
bottom of carriage are riding their switch
rail properly. See Figure 7- 1 14.
00700-CL222-05, 1 5 March 2005
Section 7. Component Procedures
7- 1 14.
Figure
Underside of Carriage
4. Position platform 3 ft. (1 m) from floor.
5. Install rocker assembly, its associated
hardware and chain on center cylinder.
See Figure 7- 1 1 5.
6. Install endcap pulley on center cylinder.
7. Feed chains for center cylinder and
over-the-mast cable.
7- 1 15.
Figure
Center C
y
linder, Top View
8. Feed over-the-mast cable through back of
carriage to carriage manager and connect
to JPC8 and JPC9.
Three-Stage Carriage