Documentation of the inverter
The following must be documented for the inverter:
● The results of the acceptance test.
● The settings of the integrated drive safety functions.
The documentation must be signed.
Who may perform the acceptance test of the inverter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the inverter.
Reduced acceptance after functions have been expanded
A full acceptance test is necessary only after first commissioning. A reduced acceptance test
is sufficient when safety functions are expanded.
Measure
Functional expansion of the
machine (additional drive).
Transfer of inverter settings to
other identical machines by means
of series commissioning.
Converter with control units CU250D-2
Operating Instructions, 04/2014, FW V4.7, A5E34261542B AA
The commissioning tool STARTER logs the settings of the integrated drive functions, if
necessary. See also Section: Documents for acceptance (Page 252).
8.9 Safe Torque Off (STO) safety function
Acceptance test
Acceptance test
Yes.
Only check the safety
functions of the new
drive.
No.
Only check the control
of all of the safety
functions.
Setting functions
Documentation
Supplement machine overview
•
Supplement inverter data
•
Add function table
•
Log the new checksums
•
Countersignature
•
Add machine description
•
Check checksums
•
Check firmware versions
•
251