Clip; Shift Cable Ball Joint; Shift Knob - Ford TRADER Workshop Manual

Truck
Table of Contents

Advertisement

J2
J2-48
SHIFT MECHANISM (TRANSMISSION)
Installation Note
Clip
1. Install the clips as shown in the figure.
Selector cable ball joint
1. Loosen the locknut.
Note
• The shift lever will
be
set in neutral position
by
force
of the spring.
2. Set the shift lever in neutral position.
3. Turn the ball joint so that the selector cable aligns with the
installation hole of the shift lever.
4. Tighten the locknut.
Tightening torque:
10-15 N-m (1.0-1.5 m-kg, 7-11 ft-Ib)
Shift cable ball joint
1. Measure A and B shown in the figure.
2. Caluculate the neutral position of the shift lever as follows:
Neutral position C
=
B
+
A
2
B
3. Hold the shift lever in neutral position.
4. Loosen the shift cable locknut.
5. Turn the ball joint so that the shift cable aligns with the in-
stallation hole of the shift lever.
6. Tighten the locknut.
Tightening torque:
10-15 N-m (1.0-1.5 m-kg, 7-11 ft-Ib)
7. After installation, verify that the shift lever operates smoothly.
Shift knob
1. Install the shift knob as shown in the figure.