2.7.3

Signal flow for commissioning example

Figure 2-12
Signal flow from initial commissioning example (chassis)
2.7.4

Commissioning with STARTER (example)

The table below describes the steps for commissioning the example with STARTER.
Table 2-9
Sequence for commissioning with STARTER (example)
What to do?
1.
Automatic
configuration
Commissioning
Commissioning Manual, (IH1), 07/2007 Edition, 6SL3097-2AF00-0BP7
2.7 Initial commissioning using vector (chassis) as an example
How to do it?
Operator action:
-> "Project"--> "Connect to target system"
-> Double-click "Automatic configuration"
-> Follow the instructions provided in the Wizard.
STARTER then automatically switches to offline
mode.
Commissioning
Remark
The DRIVE-CLiQ topology is
determined and the electronic type
plates are read. The data is then
transferred to STARTER.
The next steps are carried out
offline.
75