Commissioning
2.6 Initial commissioning using vector (booksize) as an example
2.6.3

Signal flow for commissioning example

Figure 2-10
Signal flow for initial commissioning example (booksize; vector)
2.6.4

Commissioning with STARTER (example)

The table below describes the steps for commissioning the example with STARTER.
Table 2-7
Sequence for commissioning with STARTER (example)
What to do?
1.
Automatic
configuration
Note:
When the factory setting is p7826 = 1, the FW is automatically changed to the status on the CF card when a configured
DRIVE-CLiQ component is first booted. This may take a few minutes and is indicated by the READY-LED on the
corresponding components flashing green/red and the Control Unit flashing orange (0.5 Hz). Once all updates have been
completed, the READY-LED on the Control Unit flashes orange at 2 Hz and the corresponding READY-LED on the
components flashes green/red at 2 Hz. For the firmware to be activated, a POWER ON must be carried out for the
components.
68
Operator action:
-> "Project" -> "Connect to target system"
-> Double-click "Automatic configuration"
-> Follow the instructions provided in the Wizard.
How to do it?
Commissioning Manual, (IH1), 07/2007 Edition, 6SL3097-2AF00-0BP7
Remark
Commissioning