Preparations for Commissioning

1.4 Connection via serial interface

2. Recommended connecting cable
3. Recommended connectors
1.4
Connection via serial interface
Prerequisites
There must be a serial interface (COM) on the PC from which the connection is to be made.
Settings
1. In the STARTER, go to Project > Set PC/PG interface and select the Serial cable (PPI)
interface.
If this interface is not in the selection list, you will first have to add it using Select.
Note
If the interface cannot be added to the selection menu, the driver for the serial interface
has to be installed.
This is located under the following path on the STARTER CD:
\installation\starter\starter\Disk1\SerialCable_PPI\
The STARTER must not be active while the driver is being installed.
2. Enter the following settings. The "0" address and the transmission rate (e.g. 19.2 kbit/s)
are important here.
22
– Industrial Ethernet FC TP Standard Cable GP 2 x 2 (up to max. 100 m)
Standard bus cable with rigid conductors and a special design for fast installation
Order No.: 6XV1840-2AH10
– Industrial Ethernet FC TP Flexible Cable GP 2 x 2 (up to max. 85 m)
Order No.: 6XV1870–2B
– Industrial Ethernet FC Trailing Cable GP 2 x 2 (up to max. 85 m)
Order No.: 6XV1870–2D
– Industrial Ethernet FC Trailing Cable 2 x 2 (up to max. 85 m)
Order No.: 6XV1840–3AH10
– Industrial Ethernet FC Marine Cable 2 x 2 (up to max. 85 m)
Order No.: 6XV1840–4AH10
– Industrial Ethernet FC RJ45 Plug 145 for CU320 with CBE20
Order No.: 6GK1901-1BB30-0Ax0
– Industrial Ethernet FC RJ45 Plug 180 for CU310 PN (available as of approx. July
2006)
Order No.: 6GK1901-1BB10-2Ax0
Commissioning Manual, (IH1), 07/2007 Edition, 6SL3097-2AF00-0BP7
Commissioning

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents