Operating the circuit-breaker panel
Preconditions
•
Panel prepared, no circuit-breaker truck inserted
•
Circuit-breaker truck with the same coding as panel available
•
Coupling pin of the operating shaft in vertical position
•
Spring energy store in the circuit-breaker discharged
•
High-voltage door open
•
Low-voltage connector stowed away
•
Auxiliary voltage for the panel disconnected
Fig. 155: Panel prepared to insert circuit-breaker truck
Procedure
Move the circuit-breaker truck centrally in front of the panel. The rollers (1) of the circuit-
breaker truck point towards the guide rails (2) at the bottom of the panel.
Push the circuit-breaker truck into the panel as far as it will go.
Fig. 156: Circuit-breaker truck in front of panel