8-6-25

Wagon AN Drawer Sheet Met. Assembly replacement

8-6-25-1
Preparations
When preparing for the replacement, you must perform the following steps:
ENERGY CONTROL AND POWER LOCKOUT FOR VIVID E9.
CAUTION
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO VOLTAGE
GREATER THAN 30 VOLTS:
1. TURN OFF THE BREAKER.
2. UNPLUG THE SYSTEM.
TAG
&
LOCKOUT
3. MAINTAIN CONTROL OF THE SYSTEM POWER PLUG.
Signed
Date
4. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE AS THERE ARE NO
TEST POINTS TO VERIFY ISOLATION.
Beware that the Main Power Supply and Back End Processor may be energized even if the
power is turned off when the cord is still plugged into the AC Outlet.
1.) Power down the VIVID E9.
2.) Disconnect the Mains Power Cable from the wall outlet.
3.) Disconnect all probes and external I/O cabling.
4.) Remove the Upper OP Panel/Touch Panel assembly.
5.) Remove the Lower Operator Panel.
6.) Remove the Alphanumeric Keyboard Assembly.
5