DRX Board removal procedure
Follow these steps to remove the DRX Board:
1.) Remove the DRX Shield.
2.) Pull out the DRX Board.
3.) Place it on an ESD safe place.
8-10-7-3
DRX Board installation procedure
Follow these steps to install the DRX Board:
1.) Carefully align the DRX Board with the rails and push it in till it is seated in the Back Plane
connectors.
2.) Install the DRX Shield.
3.) Install the FEP Cover and fasten it with its fixing screws.
4.) Plug in the PCIe (GFI) Cable.
5.) Install the cover for the PCIe cable.
6.) Install the Right Side Cover.
8-10-7-4
Calibration and adjustments
Calibrate the Front End as described in:
page
6-11.
8 - 240
Section 8-10 - Front End Processor (FEP) / Card Cage parts replacement
5
EVISION
Section 6-6 "DC Offset Calibration (Front End Alignment)" on
VIVID E9 S
M
ERVICE
ANUAL

Advertisement

Table of Contents
loading

Table of Contents